Skip to main content

ESDIS Weekly Metrics: February 10, 2025

Image

Note:

  1. The volume distributed to end users per day, as a running average over the last 4 weeks, is 3.025 times the volume added to the archive per day.

LANCE Data Latency

Image

Note:

Higher product latencies for:

  • OMPS-SNPP on February 4-5, 2025, due to an errant database query that slowed the database down, affecting latency.
Image
Image

Note:

  1. Latency for a data granule is defined as the time taken from the midpoint between the start and end of acquisition of the data for that granule to the granule’s being ready online for users to download.
  2. Duration covered by the data for a granule is defined differently for different instruments (e.g., MODIS granules are 5 minutes long while OMI NRT granules are 13 to 136 minutes long).
  3. Over the last 4 weeks, over 95% of NRT data requests for all instruments except for 3 instruments (OMPS-SNPP, SMAP L-BAND RADIOMETER-SMAP and VIIRS-SNPP-Land) were satisfied within 3 hours. OMPS-SNPP, SMAP L-BAND RADIOMETER-SMAP and VIIRS-SNPP-Land over 91%, 70%, and 78% of the NRT data requests were satisfied within 3 hours, respectively.

Global Imagery Browse Services (GIBS)

Image

Worldview

Image